Albany Health Campus Redevelopment
Machine-read 9
Reporting boundary
The current approved budget of $170.5m is stated as $161.6m (February 2010 election commitment) plus $8.9m Commonwealth. Expected cost ($170.8m) exceeds the current approved budget; the reported variance of $150.8m is measured against expected cost, not against the current approved budget.
Cost as published, edition by edition
What each edition said this would cost
3 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| Report 12 – October 2012 | $20mCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Report 12 – October 2012 | $170.5mCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Report 12 – October 2012 | $170.8mCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Cost
- Expenditure to date
- $120.2m Document miningMachine-read
- Reason for variance
- SCOPE CHANGE. The cost increase is due to a significantly expanded scope resulting from increased state and Commonwealth and funding. Increase in cost is also due to the cost of medical imaging department redesign and reconstruction. Document miningMachine-read
- Reason for variance
- DELAYS IN CONTRACTOR APPOINTMENT AND DELIVERY DELAYS. Late appointment of the contractor has delayed the commencement of the construction. There have been delays due to medical imaging redesign, asbestos being found during demolition and poor weather conditions. Document miningMachine-read
Delivery
- Form of procurement
- Early Contractor Involvement Document miningMachine-read
Timeline
Sources
Original documents
Document mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 38, COST table, row 'Expenditure to 30 June 2012'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 39, TIME table, row 'Original approved completion date'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 39, TIME table, row 'Current approved completion date'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 38, Appendix 3, 'Albany Health Campus Redevelopment', COST table, row 'Original approved budget'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 38, COST table, row 'Current approved budget'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 38, COST table, row 'Expected cost'
Open original source