VIC project account
Austin Health Critical infrastructure
Official 5
Reporting boundary
Victorian Department of Health reporting line for 'Austin Health Critical infrastructure' as published in the 2020-21 annual report. The unit of account is the department's own funding line. Merged from 2 records that described this project, each read from a different document. Every fact keeps its own source.
Cost as published, edition by edition
What each edition said this would cost
4 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| 2017-18 | $40.8mAs printed: 40,800 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Victorian Department of Treasury and Finance | Official |
| 2020-21 | $40.8mAs printed: 40.8 ($m)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Victorian Department of Health | Official |
| 2020-21 | $62.8mAs printed: 62.816 ($m)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Victorian Department of Health | Official |
| 2020-21 | $66.4mAs printed: 66.409 ($m)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Victorian Department of Health | Official |
Evidence history
Reported events and explanations
- June 2019
Practical completion date. Jun 2019
Source and location
Victorian Department of Health
Department of Health annual report 2020-21: capital projects completed
Sheet 'Capital projects financial completion', project row 'Austin Health Critical infrastructure', column 'Practical completion date'
Open original source: Department of Health annual report 2020-21: capital projects completed - 30 June 2021
Original approved Total Estimated Investment. recovered from a date-formatted cell. 40.8
Source and location
Victorian Department of Health
Department of Health annual report 2020-21: capital projects completed
Sheet 'Capital projects financial completion', project row 'Austin Health Critical infrastructure', column 'Original approved TEI'
Open original source: Department of Health annual report 2020-21: capital projects completed - 30 June 2021
Latest approved Total Estimated Investment. 62.816
Source and location
Victorian Department of Health
Department of Health annual report 2020-21: capital projects completed
Sheet 'Capital projects financial completion', project row 'Austin Health Critical infrastructure', column 'Latest approved TEI'
Open original source: Department of Health annual report 2020-21: capital projects completed
Sources
Original documents
Victorian Department of Treasury and Finance, Victorian Budget Paper 4 State Capital Program 2017-18
Asset investment table row 'Austin Health Critical infrastructure', column 'Total Estimated Investment'
Open original sourceVictorian Department of Health, Department of Health annual report 2020-21: capital projects completed
Sheet 'Capital projects financial completion', project row 'Austin Health Critical infrastructure', column 'Practical completion date'
Open original sourceVictorian Department of Health, Department of Health annual report 2020-21: capital projects completed
Sheet 'Capital projects financial completion', project row 'Austin Health Critical infrastructure', column 'Original approved TEI'
Open original sourceVictorian Department of Health, Department of Health annual report 2020-21: capital projects completed
Sheet 'Capital projects financial completion', project row 'Austin Health Critical infrastructure', column 'Latest approved TEI'
Open original source