Bankstown Hospital (New)
Machine-read 14
Reporting boundary
Largest single hospital project in NSW. ETC rose from $1.300bn (2024-25 edition) to $2.000bn (2025-26) and held at $2.000bn (2026-27) — a +$700m / +53.8% movement across one edition. Financial completion slipped 2030 -> 2032 -> 2033 across three consecutive editions. Chapter 4 'Start' = 2020 (planning start); Table 1.1 'Year commenced' = 2026 (construction). These two start-year conventions differ and must not be conflated. Merged from 3 records that described this project, each read from a different document. Every fact keeps its own source.
Cost as published, edition by edition
What each edition said this would cost
4 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| 2024-25 | $1.30bnAs printed: 1,300,000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2026-27 | $2bnAs printed: 2,000,000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Capital projects 2025 (first edition of this financial-audit ser | $1.30bnAs printed: 1,300 ($m)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Capital projects 2025 (first edition of this financial-audit ser | $2bnAs printed: 2,000 ($m)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Cost
- Reason for variance
- ETC increase/decrease includes additional funding, absorbed measures and/or merged projects. Document miningMachine-read
- Expenditure to date
- $20mAs printed: 20 ($m) Document miningMachine-read
- Expenditure to date
- $19.9mAs printed: 19,857,000 Document miningMachine-read
- Expenditure to date
- $42.9mAs printed: 42,897 ($'000) Document miningColumn header 'Est. Expend To 30-06-26'Machine-read
Timeline
- Completion date
- 2030 Document mining
Sources
Original documents
Document mining, NSW Budget 2024-25, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-32, 'Complete(a)' column
Open original sourceDocument mining, NSW Budget 2024-25, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, Ministry of Health, Major Works – Works in Progress, p. 4-32, row 'Bankstown Hospital (New)'
Open original sourceDocument mining, NSW Budget 2025-26, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-33, row 'Bankstown Hospital (New)(b)', 'Complete(a)' column
Open original sourceDocument mining, NSW Budget 2025-26, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, footnote (b), p. 4-37; flag (b) applied to row 'Bankstown Hospital (New)(b)' on p. 4-33
Open original sourceDocument mining, NSW Health Annual Report 2024-25 - Operations and Performance section (contains the 'Infrastructure program' per-project capital works table, report pages 73-79)
Operations and Performance, 'Infrastructure program' table, report page 74
Open original source