Better care for our community – Southside Hydrotherapy Pool – improving access to hydrotherapy services
Machine-read 1
Reporting boundary
Physical completion date printed as Aug-25, i.e. already past at the time of the 2026-27 Budget, yet the project remains a Work In Progress with $386k of 2026-27 financing. The Budget does not explain the discrepancy.
Cost as published, edition by edition
What each edition said this would cost
1 observation
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| 2026-27 | $8.5mAs printed: 8,500 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Sources
Original documents
Document mining, ACT Budget 2026-27 — Budget Statements C (Health and Community Services Directorate; Canberra Health Services), incl. Tables 21-24 and 29-31 Infrastructure Program
Statement C, Table 31 (HCSD Work In Progress), page 37
Open original source