Blacktown Hospital Stage 2 Redevelopment Main Building Works
Machine-read 3
Reporting boundary
SSD-7714 (main building works) sits under concept approval SSD-7058, which approved 40,000 sqm GFA. The main works report records a reduction to 36,500 sqm — an explicit, quotable scope movement.
Cost as published, edition by edition
What each edition said this would cost
1 observation
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| current | $289.1mAs printed: $289,100,000Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Size
- Floor area
- GFA 40,000 sqm Document miningConcept proposal envelope, to accommodate a new emergency department and operating theatresMachine-read
- Floor area
- reduction in GFA from the approved 40,000 sqm by 3,500 sqm to 36,500 sqm Document miningReduced from the 40,000 sqm approved under the concept proposalMachine-read
Sources
Original documents
Document mining, NSW Major Projects register filtered to development type 'Hospitals, medical centres and health research facilities' (464 records; 123 primary SSD applications; 150 at Determination)
SSD-7058 Secretary's Environmental Assessment Report, project table row 'GFA', PDF page 8
Open original sourceDocument mining, NSW Major Projects register filtered to development type 'Hospitals, medical centres and health research facilities' (464 records; 123 primary SSD applications; 150 at Determination)
SSD-7714 Environmental Assessment Report, project table row 'CIV', PDF page 9
Open original sourceDocument mining, NSW Major Projects register filtered to development type 'Hospitals, medical centres and health research facilities' (464 records; 123 primary SSD applications; 150 at Determination)
SSD-7714 Environmental Assessment Report, PDF page 9
Open original source