Bowral Hospital Upgrade
Machine-read 2
Reporting boundary
Exhibit 4 row. Year funded: 2017. Health 2019 lists Bowral among hospital redevelopments whose budget and financial completion date were revised because stages were combined.
Cost as published, edition by edition
What each edition said this would cost
2 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| Performance audit, final report (website version), 45 pp | $50mAs printed: 50,000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Performance audit, final report (website version), 45 pp | $50mAs printed: 50,000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Sources
Original documents
Document mining, Health capital works — NSW Auditor-General's Report to Parliament (Performance Audit)
Exhibit 4, printed p.15 (PDF p.19), 'Funding committed in 2015 $'000'
Open original sourceDocument mining, Health capital works — NSW Auditor-General's Report to Parliament (Performance Audit)
Exhibit 4, printed p.15 (PDF p.19), 'Estimated Total Cost published in the Budget Papers $'000'
Open original source