Busselton Health Campus
Machine-read 13
Reporting boundary
Original $65m was for a greenfield hospital at Vasse Newton; current $120.4m is for redevelopment of the existing Busselton Hospital site and adds a community health centre and mental health clinic. Not like-for-like. Merged from 2 records that described this project, each read from a different document. Every fact keeps its own source.
Cost as published, edition by edition
What each edition said this would cost
3 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| Report 12 – October 2012 | $65mCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Report 12 – October 2012 | $120.4mCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Wayback Machine capture 22 August 2019 | $120.4mAs printed: $120.45 millionCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Capacity
- Beds
- 80 bed Document miningMachine-read
- Beds
- 84 Document miningMachine-read
Cost
- Expenditure to date
- $5.8m Document miningMachine-read
- Reason for variance
- SCOPE CHANGE AND DELAY IN OBTAINING ENVIRONMENTAL APPROVAL. More detailed planning required due to change in project scope from new hospital on green-field site to redevelopment of the current hospital. Also, project now includes a new community health centre and mental health clinic. There were also delays in obtaining state and commonwealth environmental approvals. Document miningMachine-read
Delivery
- Form of procurement
- Design and Construct with novation of the design team (ND&C) Document mining
Sources
Original documents
Document mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 40, COST table, row 'Expenditure to 30 June 2012'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 41, TIME table, row 'Original approved completion date'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 41, TIME table, rows 'Current approved completion date' / 'Expected completion date' (variance 38 months)
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 40, Appendix 3, 'Busselton Health Campus', COST table, row 'Original approved budget'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 40, COST table, rows 'Current approved budget' and 'Expected cost'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 40, DESCRIPTION AND BACKGROUND table, 'Project description and scope'