Canterbury Hospital Redevelopment
Machine-read 9Secondary 2
Reporting boundary
Location label changed Belmore -> Campsie between the 2024-25 and 2025-26 editions, which will break a naive name+location join. ETC held at $350.0m for two editions then rose to $400.0m in 2026-27; completion 2029 -> 2029 -> 2030. Merged from 4 records that described this project, each read from a different document. Every fact keeps its own source.
Cost as published, edition by edition
What each edition said this would cost
4 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| 2024-25 | $350mAs printed: 350,000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2024-25 | $350mAs printed: $350 millionCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2026-27 | $400mAs printed: 400,000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| live site | $350mAs printed: Stage 1 project budget of $350 millionCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Secondary |
Recorded particulars
What else the sources state
Cost
- Expenditure to date
- $6mAs printed: 5,965,000 Document miningMachine-read
- Reason for variance
- ETC increase/decrease includes additional funding, absorbed measures and/or merged projects. Document miningMachine-read
- Expenditure to date
- $19.9mAs printed: 19,872 ($'000) Document miningColumn header 'Est. Expend To 30-06-26'Machine-read
Size
- Floor area
- 15,000m2 Document miningSecondary
Timeline
- Completion date
- 2029 Document mining
Sources
Original documents
Document mining, NSW Budget 2024-25, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-33, 'Complete(a)' column
Open original sourceDocument mining, NSW Budget 2024-25, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-33, row 'Canterbury Hospital Redevelopment'
Open original sourceDocument mining, NSW Health Annual Report 2024-25 - Operations and Performance section (contains the 'Infrastructure program' per-project capital works table, report pages 73-79)
Operations and Performance, 'Infrastructure program' table, report page 74
Open original sourceDocument mining, Sydney Local Health District — Year in Review 2024-25
Printed pages 50-51, section "Building our future", sub-heading "Canterbury Hospital Redevelopment"
Open original sourceDocument mining, NSW Budget 2026-27, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-37, 'Complete(a)' column
Open original source