WA project account
Central Energy Plant QEII Medical Centre
Machine-read 7
Reporting boundary
Health precinct engineering infrastructure (relocation of the central energy plant) rather than clinical floorspace, but funded and delivered under Department of Health as a major capital project. Included for completeness.
Cost as published, edition by edition
What each edition said this would cost
2 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| Report 12 – October 2012 | $220mCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Report 12 – October 2012 | $225.2mCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Cost
- Expenditure to date
- $182m Document miningMachine-read
- Reason for variance
- COST CLARIFICATION DURING PROJECT DEFINITION. After business case approval the project underwent detailed project definition to clarify project costs. This definition identified an expected cost of $225.2 million for the project, $5.2 million more than the business case estimate. Document miningMachine-read
Delivery
- Form of procurement
- Two stage managing contractor Document miningMachine-read
Timeline
- Completion date
- July 2012 Document miningMachine-read
- Completion date
- December 2012 Document mining
Sources
Original documents
Document mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 42, COST table, row 'Expenditure to 30 June 2012'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 43, TIME table, row 'Original approved completion date'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 43, TIME table, rows 'Current approved completion date' / 'Expected completion date' (variance 5 months)
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 42, Appendix 3, 'Central Energy Plant QEII Medical Centre', COST table, row 'Original approved budget'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 42, COST table, rows 'Current approved budget' and 'Expected cost'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 42, DESCRIPTION AND BACKGROUND table, row 'Procurement strategy'