NSW project account
Cooma Hospital Redevelopment
Machine-read 2
Reporting boundary
Footnote ***: final works are being delivered by the local health district, so the Health Infrastructure figure is not the whole-of-project cost.
Recorded particulars
What else the sources state
Cost
- Expenditure to date
- $23.2mAs printed: 23,227,000 Document miningFinal works are being delivered by the local health district, which includes a refurbishment and expansion of existing medical imaging unit.Machine-read
Timeline
- Completion date
- 2024 Document miningMachine-read
Sources
Original documents
Document mining, NSW Health Annual Report 2024-25 - Operations and Performance section (contains the 'Infrastructure program' per-project capital works table, report pages 73-79)
Operations and Performance, 'Infrastructure program' table, report page 76
Open original sourceDocument mining, NSW Health Annual Report 2024-25 - Operations and Performance section (contains the 'Infrastructure program' per-project capital works table, report pages 73-79)
Operations and Performance, 'Infrastructure program' table, report page 76 (footnote on page 79)
Open original source