Eurobodalla Regional Hospital Redevelopment
Machine-read 5
Reporting boundary
ETC stable at $330.0m across all three editions; completion slipped 2027 -> 2028 between 2024-25 and 2025-26 then held. Replaces services at Moruya and Batemans Bay Hospitals.
Cost as published, edition by edition
What each edition said this would cost
2 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| 2024-25 | $330mAs printed: 330,000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2026-27 | $330mAs printed: 330,000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Cost
- Expenditure to date
- $261.8mAs printed: 261,849 ($'000) Document miningColumn header 'Est. Expend To 30-06-26'Machine-read
Timeline
- Completion date
- 2027 Document miningMachine-read
- Completion date
- 2028 Document miningMachine-read
Sources
Original documents
Document mining, NSW Budget 2024-25, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-33, 'Complete(a)' column
Open original sourceDocument mining, NSW Budget 2024-25, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-33, row 'Eurobodalla Regional Hospital Redevelopment'
Open original sourceDocument mining, NSW Budget 2026-27, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-37, 'Complete(a)' column
Open original sourceDocument mining, NSW Budget 2026-27, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-37, row 'Eurobodalla Regional Hospital Redevelopment'
Open original sourceDocument mining, NSW Budget 2026-27, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-37
Open original source