WA project account
Fiona Stanley Hospital Cladding - Building B
Machine-read 2
Reporting boundary
Series 33,300 to 33,093 ($'000). Building B cladding is a separate line from the main Fiona Stanley Hospital cladding item at 15,308.
Cost as published, edition by edition
What each edition said this would cost
2 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| 2025-26 | $33.3mAs printed: 33,300 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2026-27 | $33.1mAs printed: 33,093 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Sources
Original documents
Document mining, 2025-26 Western Australia State Budget, Budget Paper No. 2, Budget Statements, Part 5: Health
p.323, Asset Investment Program table, NEW WORKS, under heading 'Cladding'
Open original sourceDocument mining, 2026-27 Western Australia State Budget, Budget Paper No. 2, Budget Statements, Part 5: Health
p.311, Asset Investment Program table, under heading 'Cladding'
Open original source