Second textbook slow slip: ETC stable at $50.0m while completion moved one year in each successive edition, 2027 -> 2028 -> 2029. Merged from 2 records that described this project, each read from a different document. Every fact keeps its own source.
Cost as published, edition by edition
What each edition said this would cost
2 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| 2024-25 | $50mAs printed: 50,000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2026-27 | $50mAs printed: 50,000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Cost
- Expenditure to date
- $10.5mAs printed: 10,536,000 Document miningMachine-read
Timeline
- Completion date
- 2027 Document miningMachine-read
- Completion date
- 2028 Document miningMachine-read
- Completion date
- 2026 Document miningMachine-read
- Completion date
- 2029 Document miningMachine-read
Sources
Original documents
Document mining, NSW Budget 2024-25, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-33, 'Complete(a)' column
Open original sourceDocument mining, NSW Budget 2024-25, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-33, row 'Glen Innes Hospital Upgrade'
Open original sourceDocument mining, NSW Budget 2025-26, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-34, 'Complete(a)' column
Open original sourceDocument mining, NSW Health Annual Report 2024-25 - Operations and Performance section (contains the 'Infrastructure program' per-project capital works table, report pages 73-79)
Operations and Performance, 'Infrastructure program' table, report page 73
Open original sourceDocument mining, NSW Budget 2026-27, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-37, 'Complete(a)' column
Open original source