VIC project account
Goulburn Valley Health redevelopment
Official 11Secondary 24 figures were withheld as unusable.
Reporting boundary
Victorian Department of Health reporting line for 'Goulburn Valley Health redevelopment – planning and development (Shepparton)' as published in the 2022-23 annual report. The unit of account is the department's own funding line. Merged from 2 records that described this project, each read from a different document. Every fact keeps its own source.
Project structure
How this record relates to other projects
Has phase
Goulburn Valley Health redevelopment — constructionConstruction funding is the TEI of a construction phase within the whole redevelopment.Source and location
Victorian Department of Treasury and Finance
Victorian Budget Paper 4 State Capital Program 2016-17
Chapter 2!A569:F569, row 'Goulburn Valley Health Redevelopment (Shepparton) (a)', column B 'Total Estimated Investment'
Open original source: Victorian Budget Paper 4 State Capital Program 2016-17Has phase
Goulburn Valley Health redevelopment — planningPlanning allocation is a phase, not the whole redevelopment TEI.Source and location
Victorian Department of Treasury and Finance
Victorian Budget Paper 4 State Capital Program 2016-17
Chapter 2!A615:F615, row 'Goulburn Valley Health redevelopment – planning and development (Shepparton)', column B 'Total Estimated Investment'
Open original source: Victorian Budget Paper 4 State Capital Program 2016-17
Project account
Reviewed baseline and final outturn
Final reported outturn
| First promised | Reviewed outcome |
|---|---|
Original estimate$169.5mAs printed: 169.525 ($m)Original approved Total Estimated Investment.Reviewed interpretationWhole-project total investment · Original estimate · vic-gvhr-whole-deliveryOfficialSource and locationVictorian Department of Health Department of Health annual report 2022-23: capital projects completed Sheet 'Capital projects practical completion', project row 'Goulburn Valley Health redevelopment – planning and development (Shepparton)', column 'Original approved TEI' Open original source: Department of Health annual report 2022-23: capital projects completed | Final reported outturn$229.3mAs printed: 229.349 ($m)Actual Total Estimated Investment cost at financial completion.Reviewed interpretationWhole-project total investment · Final reported outturn · vic-gvhr-whole-deliveryOfficialSource and locationVictorian Department of Health Department of Health annual report 2023-24: capital projects completed Sheet 'Capital projects financial completion', project row 'Goulburn Valley Health redevelopment – planning and development (Shepparton)', column 'Actual TEI cost' Open original source |
Cost as published, edition by edition
What each edition said this would cost
7 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| 2017-18 | $170.5mAs printed: 170,525 ($'000)Whole-project total investment, accepted interpretation, eligible for a project headlineReviewed interpretationWhole-project total investment · Current forecast · vic-gvhr-whole-delivery | Victorian Department of Treasury and Finance | Official |
| 2022-23 | $169.5mAs printed: 169.525 ($m)Whole-project total investment, accepted interpretation, eligible for a project headlineReviewed interpretationWhole-project total investment · Original estimate · vic-gvhr-whole-delivery | Victorian Department of Health | Official |
| 2022-23 | $229.3mAs printed: 229.349 ($m)Whole-project total investment, accepted interpretation, eligible for a project headlineReviewed interpretationWhole-project total investment · Current approved amount · vic-gvhr-whole-delivery | Victorian Department of Health |
Recorded particulars
What else the sources state
Capacity
- Beds
- 280 bed acute and extended care facility Document miningacute and extended careSecondary
Timeline
- Completion date
- 2020 Document miningSecondary
Evidence history
Reported events and explanations
- June 2021
Original completion date. Jun 2021
Source and location
Victorian Department of Health
Department of Health annual report 2022-23: capital projects completed
Sheet 'Capital projects practical completion', project row 'Goulburn Valley Health redevelopment – planning and development (Shepparton)', column 'Original completion date'
Open original source: Department of Health annual report 2022-23: capital projects completed - June 2023
Practical completion date. Jun 2023
Source and location
Victorian Department of Health
Department of Health annual report 2022-23: capital projects completed
Sheet 'Capital projects practical completion', project row 'Goulburn Valley Health redevelopment – planning and development (Shepparton)', column 'Practical completion date'
Open original source: Department of Health annual report 2022-23: capital projects completed - June 2023
Practical completion date. Jun 2023
Source and location
Victorian Department of Health
Department of Health annual report 2023-24: capital projects completed
Sheet 'Capital projects financial completion', project row 'Goulburn Valley Health redevelopment – planning and development (Shepparton)', column 'Practical completion date'
Open original source: Department of Health annual report 2023-24: capital projects completed
Sources
Original documents
Victorian Department of Treasury and Finance, Victorian Budget Paper 4 State Capital Program 2017-18
Chapter 2!A714:F714, row 'Goulburn Valley Health redevelopment – planning and development (Shepparton)', column B 'Total Estimated Investment'
Open original sourceVictorian Department of Health, Department of Health annual report 2022-23: capital projects completed
Sheet 'Capital projects practical completion', project row 'Goulburn Valley Health redevelopment – planning and development (Shepparton)', column 'Original completion date'
Open original sourceVictorian Department of Health, Department of Health annual report 2022-23: capital projects completed
Sheet 'Capital projects practical completion', project row 'Goulburn Valley Health redevelopment – planning and development (Shepparton)', column 'Practical completion date'
Open original sourceVictorian Department of Health, Department of Health annual report 2022-23: capital projects completed
Sheet 'Capital projects practical completion', project row 'Goulburn Valley Health redevelopment – planning and development (Shepparton)', column 'Latest approved completion date'