Hornsby Ku-ring-gai Hospital Redevelopment (Stages 1, 1A, 2 and 2A)
Machine-read 5
Reporting boundary
A single facility redevelopment delivered as multiple funded stages. Exhibit 4 records only the Stage 2 election commitment. The audit narrative (Chapter 4) covers Stage 1, the 2017 Stage 1 Business Case Addendum, Stage 2 and Stage 2A. Costs below are stage-specific and MUST NOT be summed into a single project total without reading the boundary text on each fact.
Cost as published, edition by edition
What each edition said this would cost
2 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| Performance audit, final report (website version), 45 pp | $200mAs printed: 200,000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Performance audit, final report (website version), 45 pp | $290.7mAs printed: $290.7 millionCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Cost
- Reason for variance
- inappropriate use of around $11.0 million in Stage 1 contingency for originally unfunded works contrary to Treasury policy; the additional $16.4 million cost unforeseen in the Stage 1 business case for delivering medical imaging services mostly funded through the sale of land; an additional $15.0 million from Stage 2A to cover the budget overrun in Stage 2 due to adverse site conditions. Document miningThe audit states the cumulative effect was that Stages 1 and 2 cost approximately $42.4 million (around 14 per cent) more than they should have, once surplus Stage 1 funds are accounted for. Note the source sentence contains a typographical omission ('cost approximately $42.4 million than it should have').Machine-read
- Reason for variance
- adverse site conditions during demolition works resulted in an 11-month delay for delivering the medical imaging unit and 14-month delay completing Stage 2 main works including need for additional $15.0 million in funds to cover the resultant budget deficit for the project. Document miningMachine-read
Timeline
- Completion date
- Stage 1 was completed in 2015 Document miningMachine-read
Sources
Original documents
Document mining, Health capital works — NSW Auditor-General's Report to Parliament (Performance Audit)
Exhibit 4, printed p.15 (PDF p.19), 'Funding committed in 2015 $'000' — row 'Hornsby Ku-ring-gai Hospital / Redevelopment of Stage 2'
Open original sourceDocument mining, Health capital works — NSW Auditor-General's Report to Parliament (Performance Audit)
Chapter 4, printed p.27 (PDF p.31)
Open original sourceDocument mining, Health capital works — NSW Auditor-General's Report to Parliament (Performance Audit)
Chapter 4, heading 'Need for increased transparency and accountability in the management of contingency funds', printed p.26 (PDF p.30)
Open original sourceDocument mining, Health capital works — NSW Auditor-General's Report to Parliament (Performance Audit)
Chapter 4, three-bullet list under 'The extent of budget variation...', printed p.27–28 (PDF p.31–32)
Open original source