Integrated Mental Health Complex at Westmead
Machine-read 7
Reporting boundary
ETC stable at $540.0m across all three editions; completion pulled in 2031 -> 2030 between 2024-25 and 2025-26. Chapter 4 'Start' 2022 vs Table 1.1 'Year commenced' 2023. Merged from 2 records that described this project, each read from a different document. Every fact keeps its own source.
Cost as published, edition by edition
What each edition said this would cost
2 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| 2024-25 | $540mAs printed: 540,000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2026-27 | $540mAs printed: 540,000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Cost
- Expenditure to date
- $138.7mAs printed: 138,680,000 Document miningMachine-read
- Expenditure to date
- $249.1mAs printed: 249,098 ($'000) Document miningColumn header 'Est. Expend To 30-06-26'Machine-read
Timeline
- Completion date
- 2031 Document miningMachine-read
- Completion date
- 2027 Document miningMachine-read
- Completion date
- 2030 Document miningMachine-read
Sources
Original documents
Document mining, NSW Budget 2024-25, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-34, 'Complete(a)' column
Open original sourceDocument mining, NSW Budget 2024-25, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-34, row 'Integrated Mental Health Complex at Westmead(b)'
Open original sourceDocument mining, NSW Health Annual Report 2024-25 - Operations and Performance section (contains the 'Infrastructure program' per-project capital works table, report pages 73-79)
Operations and Performance, 'Infrastructure program' table, report page 77
Open original sourceDocument mining, NSW Budget 2026-27, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-38, 'Complete(a)' column
Open original sourceDocument mining, NSW Budget 2026-27, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-38, row 'Integrated Mental Health Complex at Westmead'
Open original source