Joondalup Health Campus – Stage 1 Redevelopment
Machine-read 8
Reporting boundary
Expenditure to 30 June 2012 ($166.9m) exceeds the original approved budget ($122.67m) but sits within the current approved budget ($229.8m). Original budget was announced before a business case existed. Managing contractor was engaged by the private operator (Ramsay Health Care), not directly by the State.
Cost as published, edition by edition
What each edition said this would cost
2 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| Report 12 – October 2012 | $122.7mAs printed: $122.67mCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Report 12 – October 2012 | $229.8mCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Capacity
- Beds
- 477 (including 20 day renal places) Document miningTotal public bed capacity after Stage 1, up from 280, and including 20 day renal places.Machine-read
Cost
- Expenditure to date
- $166.9m Document miningMachine-read
- Reason for variance
- COST CLARIFICATION DURING PROJECT DEFINITION. Original project budget announced prior to business case. Following approval of the business case, the project underwent detailed project definition to clarify project costs. This resulted in the current approved budget of $229.8m. Document miningMachine-read
Delivery
- Form of procurement
- Managing contractor (engaged by Ramsey Health Care) Document miningMachine-read
Timeline
Sources
Original documents
Document mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 54, COST table, row 'Expenditure to 30 June 2012'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 55, TIME table, row 'Original approved completion date'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 55, TIME table, row 'Current approved completion Date'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 54, Appendix 3, 'Joondalup Health Campus – Stage 1 Redevelopment', COST table, row 'Original approved budget'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 54, COST table, rows 'Current approved budget' and 'Expected cost'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 54, DESCRIPTION AND BACKGROUND table, 'Project description and scope'
Open original source