Karratha Health Campus
Machine-read 12
Reporting boundary
DISCREPANCY IN SOURCE: the cost table row reads 'Expenditure to 30 June 2012 $0.08m' while the chart annotation on the same page reads '$0.8m'. Expenditure to date is therefore deliberately NOT recorded. Business case and PDP estimates ($239.3m) are HIGHER than the current approved budget ($207.2m). Merged from 2 records that described this project, each read from a different document. Every fact keeps its own source.
Cost as published, edition by edition
What each edition said this would cost
4 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| Report 12 – October 2012 | $150mCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Report 12 – October 2012 | $207.2mCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Report 12 – October 2012 | $239.3mAs printed: 239.3 ($m)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Wayback Machine capture 22 August 2019 | $207.2mAs printed: $207.2 millionCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Capacity
- Beds
- 40 Document miningMachine-read
Cost
- Reason for variance
- SCOPE CHANGE. Significant project scope change from the original plan of refurbishing the existing hospital to the construction of a new hospital including a helipad. Document miningMachine-read
Delivery
- Form of procurement
- To be decided Document miningMachine-read
- Form of procurement
- Two Stage Managing Contractor (MC) Document miningMachine-read
Team
- Building contractor
- Multiplex Constructions Pty Ltd Document mining
Sources
Original documents
Document mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 57, TIME table, row 'Original approved completion date'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 57, TIME table, rows 'Current approved completion date' / 'Expected completion date' (variance 24 months)
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 56, Appendix 3, 'Karratha Health Campus', COST table, row 'Original approved budget'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 56, COST table, rows 'Current approved budget' and 'Expected cost'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 57, chart 'Cost Variation By Phase $m' – Evaluation Phase (Business Case) 239.3 and Definition Phase (Project Definition Plan) 239.3
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012