Original $35 million 2017-18 commitment; estimated total cost shown as $37.386 million in both the 2022-23 and 2023-24 tables.
Cost as published, edition by edition
What each edition said this would cost
2 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| 2022-23 Budget | $35mAs printed: $35 millionCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2022-23 Budget | $37.4mAs printed: 37 386 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Timeline
- Completion date
- mid-2024 Document miningMachine-read
Sources
Original documents
Document mining, 2022-23 Budget Paper No 2, Chapter 5 - Department of Health
Chapter 5, narrative heading 'Mersey Community Hospital Capital Upgrades'
Open original sourceDocument mining, 2022-23 Budget Paper No 2, Chapter 5 - Department of Health
Table 5.5: Capital Investment Program, 'Estimated Total Cost' column ($'000)