SA project account
Metropolitan mental health beds (TQEH) - 24 beds at the Queen Elizabeth Hospital
Machine-read 21 figure was withheld as unusable.
Reporting boundary
The variance table at p.213 prints the row as 'Metropolitan mental health beds (TQEH)'; the performance table at p.21 separately lists '24 beds at the Queen Elizabeth Hospital' under 'Metropolitan Mental Health Beds'. I have treated these as the same project; the report does not explicitly equate them. The variance figure is printed in parentheses, i.e. UNFAVOURABLE. No cost, area, architect or builder disclosed.
Recorded particulars
What else the sources state
Capacity
- Beds
- 24 beds at the Queen Elizabeth Hospital Document miningMachine-read
Timeline
- Completion date
- August 2025 Document miningpractical completion, expected (not achieved at reporting date)Machine-read
Sources
Original documents
Document mining, Department for Health and Wellbeing 2024-25 Annual Report
Section 'Agency specific objectives and performance', row 'Mental Health and Drug and Alcohol Rehabilitation', PDF/printed p.21
Open original source