NSW project account
Nepean Hospital Redevelopment
Machine-read 1
Reporting boundary
Nepean Blue Mountains LHD. No capital cost is disclosed in the district's 2024-25 audited statements. The only redevelopment-specific disclosure is an operating-expense variance attributed in part to the unfunded annualised cost of the redevelopment, alongside increased demand and the Hawkesbury hospital transition. That is a recurrent-cost consequence of the project, not a capital figure.
Recorded particulars
What else the sources state
Cost
- Reason for variance
- Expenses exceeded budget primarily due to increased demand, Hawkesbury hospital transition and unfunded annualised cost of Nepean hospital redevelopment. Document miningMachine-read
Sources
Original documents
Document mining, Nepean Blue Mountains Local Health District — Annual Financial Statements for the year ended 30 June 2025 (audited)
Page 46, Note 30 Adjusted budget review, "Net result" commentary
Open original source