New Children's Hospital (Perth Children's Hospital)
Machine-read 8
Reporting boundary
The original $206.8m and current $1 168.7m budgets are for materially different projects (relocation of Princess Margaret Hospital into Royal Perth Hospital buildings vs a new build at QEII); OAG states 'This is effectively a completely different project'. The $1.23 billion 2017-18 figure is an accounting capitalisation on handover, not an audited final project cost, and is on a different basis from the 2012 budget figures.
Cost as published, edition by edition
What each edition said this would cost
3 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| Report 12 – October 2012 | $206.8mCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Report 12 – October 2012 | $1.17bnAs printed: $1 168.7mCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Report 12 – October 2012 | $1.17bnAs printed: 1170 ($m)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Cost
- Expenditure to date
- $86.3m Document miningMachine-read
- Reason for variance
- SCOPE CHANGE. The original $206.8 million budget was for the relocation of Princess Margaret Hospital to Royal Perth Hospital. The current approved budget is based on a completely new build on the QEII Medical Centre site. This is effectively a completely different project. Document miningMachine-read
Delivery
- Form of procurement
- Two stage managing contractor Document miningMachine-read
Timeline
- Completion date
- September 2015 Document miningMachine-read
- Completion date
- December 2016 Document mining
Sources
Original documents
Document mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 60, COST table, row 'Expenditure to 30 June 2012'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 61, TIME table, rows 'Current approved Completion date' / 'Expected completion date' (variance -15 months)
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 61, TIME table, row 'Original approved completion date'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 60, Appendix 3, 'New Children's Hospital', COST table, row 'Original approved budget' and 'Reasons for cost variance'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 60, COST table, row 'Current approved budget'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 61, chart 'Cost Variation By Phase $m' – Evaluation Phase (Business Case) 1170 and Definition Phase (Project Definition Plan) 1170