SA project account
New SA Ambulance Emergency Operations Centre and Ambulance Station
Machine-read 1
Reporting boundary
The variance table at p.213 separately lists 'New ambulance headquarters' with an unfavourable variance of (11.2) $ million. That row is kept as a separate project record below because the report never explicitly states the two are the same project. A follow-up should confirm identity before merging. No cost, area, architect, builder or procurement model disclosed.
Recorded particulars
What else the sources state
Timeline
- Completion date
- October 2025 Document miningPractical Completion date; a separate 'Early Access' milestone of August (2025) is stated for the Emergency Operations CentreMachine-read
Sources
Original documents
Document mining, Department for Health and Wellbeing 2024-25 Annual Report
Section 'Agency specific objectives and performance', row 'Investment in SA Ambulance Service', PDF/printed p.19