New Women's and Children's Hospital (nWCH)
Machine-read 14
Reporting boundary
Single named hospital project managed by a project team inside the Department for Health and Wellbeing (not DIT, the usual delivery agency). Costs are capitalised in the Women's and Children's Health Network Incorporated (WCHN) financial report and consolidated into SA Health. The site is 5.697 hectares (land area, not a floor-area figure). The report explicitly states the $250m capital works in progress is 'not all of the costs of the project'. Merged from 3 records that described this project, each read from a different document. Every fact keeps its own source.
Cost as published, edition by edition
What each edition said this would cost
7 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| 2023-24 | $3.25bnAs printed: 3 247 698 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2024-25 | $3.20bnAs printed: 3 201 316 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2025-26 | $3.20bnAs printed: 3 200 944 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2026-27 | $3.22bnAs printed: 3 222 966 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Report 8 of 2025, Part A (amended version, republished November | $1.95bnAs printed: $1.95 billionCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Report 8 of 2025, Part A (amended version, republished November | $2.05bnAs printed: $2.05 billionCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Report 8 of 2025, Part A (amended version, republished November | $3.20bnAs printed: $3.2 billionCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Capacity
- Beds
- 414 overnight beds Document miningMachine-read
- Beds
- 414 beds Document miningMaster Plan released May 2023; '56 more overnight beds than the current Women's and Children's Hospital', plus 'capacity for a further 20 beds in the future'Machine-read
Cost
- Reason for variance
- $73.1mAs printed: 73.1 ($m) Document miningMachine-read
- Reason for variance
- Delays in starting construction Document miningMachine-read
- Reason for variance
- These risks are already evident in the T2D project and the new Women's and Children's Hospital, with significant cost and timing revisions made to both projects in the 2022-23 MYBR.
Sources
Original documents
Document mining, State Budget 2023-24 Agency Statements, Budget Paper 4 Volume 3
BP4 Vol 3, Health and Wellbeing, Investing expenditure summary, Existing projects, p. 16
Open original sourceDocument mining, State Budget 2024-25 Agency Statements, Budget Paper 4 Volume 3
BP4 Vol 3, Health and Wellbeing, Investing expenditure summary, Existing projects, p. 17
Open original sourceDocument mining, State Budget 2025-26 Agency Statements, Budget Paper 4 Volume 3
BP4 Vol 3, Health and Wellbeing, Investing expenditure summary, Existing projects, p. 17