Orange and Associated Health Services Public Private Partnership
Machine-read 14
Reporting boundary
Capital works are all on the Bloomfield campus at Orange, plus refurbishment of ward 18, ward 19, the Canobolas Building and the Amaroo Building. The same deed also covers facilities management only for the separately-procured new Bathurst Hospital (built by John Holland under a contract outside this deed), so whole-of-contract figures are not purely an Orange building cost.
Cost as published, edition by edition
What each edition said this would cost
7 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| Live page, copyright notice 2026 | $256mAs printed: $256 millionCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Updated as at 30 June 2010, supersedes the 2008 audited contract | $236mAs printed: $236 millionCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Updated as at 30 June 2010, supersedes the 2008 audited contract | $19mAs printed: $19 millionCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Updated as at 30 June 2010, supersedes the 2008 audited contract | $1.4mAs printed: $1.4 millionCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Updated as at 30 June 2010, supersedes the 2008 audited contract | $40.9mAs printed: $40.94MCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Updated as at 30 June 2010, supersedes the 2008 audited contract | $530.8mAs printed: $530.8 mCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Updated as at 30 June 2010, supersedes the 2008 audited contract | $600.9mAs printed: $600.9 mCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Cost
- Reason for variance
- the Government approved the business case to expand the Orange facilities to accommodate extra services including: Six medical/surgical beds, Four cardiovascular beds, Four renal dialysis chairs and Six chemotherapy treatment chairs Document miningMachine-read
- Reason for variance
- $41 million of the agreed capital cost for the extended works was paid outside of the project financing. Document miningMachine-read
Delivery
- Form of procurement
- public private partnership (PPP); Project Company Pinnacle Healthcare (OAHS) Pty Ltd designs, builds and finances the new Orange Hospital and provides facilities management Document miningMachine-read
Schedule
- Construction start
- The Project reached contract execution and financial close on 21 December 2007. Document miningMachine-read
Sources
Original documents
Document mining, Orange and Associated Health Services Public Private Partnership - Updated Summary of contracts as at 30 June 2010
Section 2.4 'Execution of the contracts', p6
Open original sourceDocument mining, Orange and Associated Health Services Public Private Partnership - Updated Summary of contracts as at 30 June 2010
Section 6, Amended Table 4 'Orange PPP - Work Program', column 'Target Completion Date', p20
Open original sourceDocument mining, Orange and Associated Health Services Public Private Partnership - Updated Summary of contracts as at 30 June 2010
Section 1.1 'Background', first bullet, p1
Open original sourceDocument mining, Orange and Associated Health Services Public Private Partnership - Updated Summary of contracts as at 30 June 2010
Section 1.1 'Background', second bullet, p1
Open original sourceDocument mining, Orange and Associated Health Services Public Private Partnership - Updated Summary of contracts as at 30 June 2010
Section 1.1 'Background', third bullet, p1
Open original source