PathWest Laboratory Medicine WA Stage 1
Machine-read 10
Reporting boundary
One of the few projects whose budget fell. Note the current approved budget ($58.3m) sits BELOW the expected cost ($59.8m) in the same table. The 9 000 sqm figure carries no stated area convention.
Cost as published, edition by edition
What each edition said this would cost
4 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| Report 12 – October 2012 | $71.4mCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Report 12 – October 2012 | $54.4mAs printed: $54.4 millionCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Report 12 – October 2012 | $58.3mCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| Report 12 – October 2012 | $59.8mCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Cost
- Expenditure to date
- $39.8m Document miningMachine-read
- Reason for variance
- TENDER SAVINGS AND SCOPE CHANGE. $17 million saving at tender, which resulted in the approved budget dropping to $54.4 million. After the contract to construct was awarded the Department of Health changed the scope of the project to include paediatric pathology. This increased the budget to $58.3 million. Document miningMachine-read
Delivery
- Form of procurement
- Construct only Document miningMachine-read
Size
- Floor area
- approximately 9 000m² Document miningComprises a basement level, six above ground levels, and a roof level plant room. The source does not say which area convention (GFA/GBA/GDA) applies.Machine-read
Sources
Original documents
Document mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 62, COST table, row 'Expenditure to 30 June 2012'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 63, TIME table, row 'Original approved completion date'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 63, TIME table, row 'Current approved completion date' (expected completion date November 2012)
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 62, Appendix 3, 'PathWest Laboratory Medicine WA Stage 1', COST table, row 'Original approved budget'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 62, COST table, row 'Reasons for cost variance'
Open original sourceDocument mining, Major Capital Projects (Performance Audit), Report 12 – October 2012
page 62, COST table, row 'Current approved budget' and 'Reasons for cost variance'
Open original source