NSW project account
Rouse Hill Hospital
Machine-read 10
Reporting boundary
ETC moved $700.0m -> $790.0m -> $910.0m across the 2024-25, 2025-26 and 2026-27 editions. The 2025-26 edition explicitly documents the cause of the final step: a $120.0m Commonwealth contribution excluded from the $790.0m figure. Chapter 4 'Start' = 2018 (planning); Table 1.1 'Year commenced' = 2026 (construction). Merged from 2 records that described this project, each read from a different document. Every fact keeps its own source.
Cost as published, edition by edition
What each edition said this would cost
3 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| 2024-25 | $700mAs printed: 700,000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2025-26 | $790mAs printed: 790,000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2026-27 | $910mAs printed: 910,000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Cost
- Reason for variance
- This excludes a $120.0 million Australian Government contribution that has been announced but not yet finalised in a formal funding agreement. The Australian Government funding will increase the total investment for the project to $910.0 million. Document miningExplicit statement of what the prior $790.0m ETC excludedMachine-read
- Expenditure to date
- $76mAs printed: 76,037,000 Document miningMachine-read
- Expenditure to date
- $114.3mAs printed: 114,304 ($'000) Document miningColumn header 'Est. Expend To 30-06-26'Machine-read
Schedule
- Construction start
- 2026 Document miningNarrative states construction commencement, distinct from Chapter 4 planning 'Start' of 2018Machine-read
Sources
Original documents
Document mining, NSW Budget 2024-25, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-35, 'Complete(a)' column
Open original sourceDocument mining, NSW Budget 2024-25, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-35, row 'Rouse Hill Hospital(b)'
Open original sourceDocument mining, NSW Budget 2025-26, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, p. 4-36, row 'Rouse Hill Hospital(b)(g)'; footnote (g) p. 4-37
Open original sourceDocument mining, NSW Budget 2025-26, Budget Paper No.03 – Infrastructure Statement
Chapter 4, Health, footnote (g), p. 4-37
Open original sourceDocument mining, NSW Health Annual Report 2024-25 - Operations and Performance section (contains the 'Infrastructure program' per-project capital works table, report pages 73-79)
Operations and Performance, 'Infrastructure program' table, report page 74
Open original source