Extracted from NSW Health Annual Report 2024-25 - Operations and Performance section (contains the 'Infrastructure program' per-project capital works table, report pages 73-79) by automated document mining (DM-003). Not reviewed by a person.
Recorded particulars
What else the sources state
Cost
- Expenditure to date
- $269.1mAs printed: 269,092,000 Document miningMachine-read
Timeline
- Completion date
- 2027 Document miningMachine-read
Sources
Original documents
Document mining, NSW Health Annual Report 2024-25 - Operations and Performance section (contains the 'Infrastructure program' per-project capital works table, report pages 73-79)
Operations and Performance, 'Infrastructure program' table, report page 76
Open original source