The Queen Elizabeth Hospital Redevelopment Stage 3
Machine-read 5
Reporting boundary
Drops out of the table after the 2025-26 edition. 2025-26 footnote (g): practical completion in 2023-24, financial finalisation in 2024-25.
Cost as published, edition by edition
What each edition said this would cost
3 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| 2023-24 | $310.1mAs printed: 310 126 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2024-25 | $309.9mAs printed: 309 861 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2025-26 | $303.3mAs printed: 303 318 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Timeline
- Completion date
- Dec 2024 Document miningMachine-read
- Completion date
- Jun 2024 Document miningFootnote (g): project practical completion date in 2023-24, financial finalisation in 2024-25.Machine-read
Sources
Original documents
Document mining, State Budget 2023-24 Agency Statements, Budget Paper 4 Volume 3
BP4 Vol 3, p. 17, 'Estimated completion Quarter' column
Open original sourceDocument mining, State Budget 2023-24 Agency Statements, Budget Paper 4 Volume 3
BP4 Vol 3, Health and Wellbeing, Investing expenditure summary, Existing projects, p. 17
Open original sourceDocument mining, State Budget 2024-25 Agency Statements, Budget Paper 4 Volume 3
BP4 Vol 3, Health and Wellbeing, Investing expenditure summary, Existing projects, p. 17
Open original sourceDocument mining, State Budget 2025-26 Agency Statements, Budget Paper 4 Volume 3
BP4 Vol 3, p. 17 row and p. 18 footnote (g)
Open original sourceDocument mining, State Budget 2025-26 Agency Statements, Budget Paper 4 Volume 3