Cost as published, edition by edition
What each edition said this would cost
2 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| 2023-24 | $12mAs printed: 12,000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Queensland Treasury | Official |
| 2024-25 | $12mAs printed: 12,000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Queensland Treasury | Official |
Sources
Original documents
Queensland Treasury, Queensland Budget Paper 3 Capital Statement 2023-24
CSV row Project Name='Cairns Bay Village Project', column 'Total Estimated Cost'
Open original sourceQueensland Treasury, Queensland Budget Paper 3 Capital Statement 2024-25
CSV row Project Name='Cairns Bay Village Project', column 'Total Estimated Cost'