NSW project account
Lifehouse at the Royal Prince Alfred Hospital (the new Sydney Cancer Centre)
Machine-read 3
Reporting boundary
HHF funding column is the Commonwealth Health and Hospitals Fund contribution only, not total project cost. Round 1, announced May 2009. Total project budget figures at paragraph 4.19 are separate from the HHF contribution.
Project account
Reviewed baseline and latest estimate
No reviewed whole-project TEI headline
| First promised | Reviewed outcome |
|---|---|
Original estimate$310mAs printed: $310 millionThe original total project budget of $310 million was reduced to $181 million with the key change that there would be no in-patient facilities within the Lifehouse.Reviewed interpretationWhole-project total investment · Original estimate · lifehouse-original-whole-projectMachine-readSource and locationDocument mining ANAO Audit Report No.45 2011-12: Administration of the Health and Hospitals Fund Paragraph 4.19, p. 98 The original total project budget of $310 million was reduced to $181 million with the key change that there would be no in-patient facilities within the Lifehouse. Open original source: ANAO Audit Report No.45 2011-12: Administration of the Health and Hospitals Fund | No reviewed whole-project TEI headlineNot reported |
Direct change
Not directly comparableComparison status
Comparison unresolved. Reason not reported.
Cost as published, edition by edition
What each edition said this would cost
2 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| Audit Report No.45 2011-12; ISBN 0 642 81253 5; ISSN 1036-7632 | $100mAs printed: 100.0 ($m)Funding contribution, accepted interpretation, not selected as a project headlineReviewed interpretationFunding contribution · Original estimate · lifehouse-hhf-contribution | Document mining | Machine-read |
| Audit Report No.45 2011-12; ISBN 0 642 81253 5; ISSN 1036-7632 | $310mAs printed: $310 millionWhole-project total investment, accepted interpretation, eligible for a project headlineReviewed interpretationWhole-project total investment · Original estimate · lifehouse-original-whole-project | Document mining | Machine-read |
Recorded particulars
What else the sources state
Cost
- Reason for variance
- At the time of application, the Chris O'Brien Lifehouse at the Royal Prince Alfred Hospital project was submitted on the basis that $100 million would be provided by a co-contributor and from public donations. This non-HHF funding failed to eventuate, with the result that in July 2009 the applicant proposed to implement the project in stages. Document miningMachine-read
Sources
Original documents
Document mining, ANAO Audit Report No.45 2011-12: Administration of the Health and Hospitals Fund
Appendix 2, Table A 1 'Projects approved for HHF funding as announced by Government', p. 140 (Round 1, NSW)
Open original sourceDocument mining, ANAO Audit Report No.45 2011-12: Administration of the Health and Hospitals Fund
Paragraph 4.19, p. 98
Open original source