SA project account
New Modbury Hospital Cancer Centre
Machine-read 1
Reporting boundary
Scope stated as '12 chemotherapy treatment spaces'. Chemotherapy treatment spaces are not beds and no matching field exists, so that number is noted here rather than recorded as a 'beds' fact. No cost, area, architect, builder or procurement model disclosed.
Recorded particulars
What else the sources state
Timeline
- Completion date
- February 2026 Document miningPractical Completion (construction in progress at reporting date)Machine-read
Sources
Original documents
Document mining, Department for Health and Wellbeing 2024-25 Annual Report
Section 'Agency specific objectives and performance', row 'Improving cancer health outcomes in South Australia', PDF/printed p.22
Open original source