Royal Darwin Hospital – additional clinical spaces
Machine-read 5
Reporting boundary
Approved as a NEW work in 2022-23 at 8 000 ($000). The revoted balance FELL to 7 137 in 2023-24 then ROSE to 24 770 in 2024-25 — a movement of roughly +$17.6 million against an $8 million original approval. The budget papers state no reason for the increase. Absent from the 2025-26 and 2026-27 tables.
Cost as published, edition by edition
What each edition said this would cost
4 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| 2022-23 (oldest edition read). Health table printed p.20 | $8mAs printed: 8 000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2023-24. Health table printed p.18 | $7.1mAs printed: 7 137 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2024-25. Health table printed pp.29-30; Health narrative pp.6-7 | $24.8mAs printed: 24 770 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2024-25. Health table printed pp.29-30; Health narrative pp.6-7 | $24.8mAs printed: $24.8 millionCapital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Schedule
- Construction start
- Q4, 2022 Document miningMachine-read
Sources
Original documents
Document mining, Northern Territory 2022-23 Budget, Budget Paper No. 4 – The Infrastructure Program
p.20, Department of Health table, 'Start date' column, under 'New works in 2022-23'
Open original sourceDocument mining, Northern Territory 2022-23 Budget, Budget Paper No. 4 – The Infrastructure Program
p.20, Department of Health table, 'Program $000' column, under 'New works in 2022-23' / Greater Darwin
Open original sourceDocument mining, Northern Territory 2023-24 Budget, Budget Paper No. 4 – The Infrastructure Program
p.18, Department of Health table, 'Program $000' column, under 'Revoted works from 2022-23' / Greater Darwin / Royal Darwin Hospital
Open original sourceDocument mining, Northern Territory 2024-25 Budget, Budget Paper No. 4 – The Infrastructure Program
p.29, Department of Health table, 'Program $000' column, under 'Revoted works from 2023-24' / Greater Darwin / Royal Darwin Hospital
Open original sourceDocument mining, Northern Territory 2024-25 Budget, Budget Paper No. 4 – The Infrastructure Program
p.7, Overview chapter, 'Health' section, 'Significant continuing works in 2024-25' bullet list