NT project account
Royal Darwin Hospital – mental health inpatient unit (from 2025-26 titled: Mental health inpatient unit, and stabilisation assessment and referral area facility)
Machine-read 6
Reporting boundary
Listed in every edition read as a REVOTED work, so the original approved cost is in an edition earlier than 2022-23 and was not seen. From the 2025-26 edition the line merges the previously separate 'Establish mental health stabilisation assessment and referral area unit' line into one item, so figures before and after 2024-25 are not on the same scope basis. Footnoted in BP4 as jointly funded by the Territory and Commonwealth.
Project account
Reviewed baseline and latest estimate
Current forecast
| First promised | Reviewed outcome |
|---|---|
| Original estimateNot reported | Current forecast$49.3mAs printed: 49 276 ($'000)Mental health inpatient unit and stabilisation assessment and referral area facility2 49 276Reviewed interpretationWhole-project total investment · Current forecast · rdh-mental-health-inpatient-unitMachine-readSource and locationDocument mining Northern Territory 2025-26 Budget, Budget Paper No. 4 – The Infrastructure Program p.24, Department of Health table, 'Program $000' column, under 'Revoted works from 2024-25' / Greater Darwin / Royal Darwin Hospital Mental health inpatient unit and stabilisation assessment and referral area facility2 49 276 Open original source: Northern Territory 2025-26 Budget, Budget Paper No. 4 – The Infrastructure Program |
Direct change
Not directly comparableComparison status
Not applicable. Reason not reported.
Cost as published, edition by edition
What each edition said this would cost
6 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| 2022-23 (oldest edition read). Health table printed p.20 | $28.9mAs printed: 28 920 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2023-24. Health table printed p.18 | $39.4mAs printed: 39 354 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2024-25. Health table printed pp.29-30; Health narrative pp.6-7 | $25.1mAs printed: 25 127 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Sources
Original documents
Document mining, Northern Territory 2022-23 Budget, Budget Paper No. 4 – The Infrastructure Program
p.20, Department of Health table, 'Program $000' column, under 'Revoted works from 2021-22' / Greater Darwin / Royal Darwin Hospital
Open original sourceDocument mining, Northern Territory 2023-24 Budget, Budget Paper No. 4 – The Infrastructure Program
p.18, Department of Health table, 'Program $000' column, under 'Revoted works from 2022-23' / Greater Darwin / Royal Darwin Hospital
Open original sourceDocument mining, Northern Territory 2024-25 Budget, Budget Paper No. 4 – The Infrastructure Program
p.29, Department of Health table, 'Program $000' column, under 'Revoted works from 2023-24' / Greater Darwin / Royal Darwin Hospital
Open original sourceDocument mining, Northern Territory 2025-26 Budget, Budget Paper No. 4 – The Infrastructure Program
p.24, Department of Health table, 'Program $000' column, under 'Revoted works from 2024-25' / Greater Darwin / Royal Darwin Hospital
Open original sourceDocument mining, Northern Territory 2025-26 Budget, Budget Paper No. 4 – The Infrastructure Program