Royal Hobart Hospital Redevelopment - Expanded Stage 2
Machine-read 10
Reporting boundary
Includes a full refurbishment of A-Block, second stage of the expanded Emergency Department and paediatric outpatients relocation. Part of a 30-year Masterplan for the RHH precinct. Merged from 2 records that described this project, each read from a different document. Every fact keeps its own source.
Cost as published, edition by edition
What each edition said this would cost
3 observations
| Edition | Published figure | Publisher | Evidence |
|---|---|---|---|
| 2022-23 Budget | $110mAs printed: 110 000 ($'000)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2026-27 | $118.4mAs printed: 118.4 ($m)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
| 2026-27 Budget (most recent) | $118.4mAs printed: 118.4 ($m)Capital meaning not yet reviewedInterpretation statusNot yet classified · Not stated | Document mining | Machine-read |
Recorded particulars
What else the sources state
Schedule
- Construction start
- 2023 Document miningMachine-read
Timeline
- Completion date
- 2028 Document miningMachine-read
- Completion date
- 2029 Document miningMachine-read
- Completion date
- late 2026 Document miningMachine-read
- Completion date
- early 2028 Document miningMachine-read
Sources
Original documents
Document mining, 2022-23 Budget Paper No 2, Chapter 5 - Department of Health
Table 5.5: Capital Investment Program, 'Estimated Total Cost' column ($'000)
Open original sourceDocument mining, 2023-24 Budget Paper No 2, Chapter 4 - Department of Health
Chapter 4, narrative heading 'Royal Hobart Hospital Redevelopment - Expanded Stage 2'
Open original sourceDocument mining, 2024-25 Tasmanian Budget, Budget Paper No. 1 (Infrastructure Investment, Table 6.3 Infrastructure Investment Project Details by Agency; Table 6.6 Future Infrastructure Projects Contingent on Australian Government Funding)
Table 6.3 (continued), 'Complete' column, Health (continued), p.129
Open original sourceDocument mining, 2026-27 Budget Paper No 1, Chapter 7 - Infrastructure Investment
Budget Paper No 1, Table 7.4, 'Start' column
Open original sourceDocument mining, 2026-27 Tasmanian Budget, Budget Paper No. 2 — Agency Information Supporting Appropriation Bill No. 1 (Chapter 5 Department of Health, Table 5.4 Capital Investment Program)
Chapter 5 Health, heading 'Royal Hobart Hospital Redevelopment - Expanded Stage 2', first bullet (A-Block Lift Replacement), p.100